1.some team leaders think that the only way to ()their team is through cash incentives. However research proves that money is the last thing you would want to use
A.arouse
B.encourage
C.incite
D.motivate
【答案】D
【解析】
一些团队主管认为唯一可以()团队的方式是现金激励。然而研究表明,金钱往往是最后选择使用的手段
A.引起
B.鼓励
C.刺激
D.激励
2.In the () phase team members begin to work together and adjust their work habits and behaviors to support the team. The team learns to trust each other
A.storming
B.performing
C.norming
D.adjourning
【答案】C
【解析】
在()阶段,团队成员开始一起协调工作并调整他们的工作习惯和行为来支持团队工作。团队开始学会相互信任
A.风暴
B.表现
C.规范
D.解散
3.Software configuration management (SCM) is the task of tracking and controlling changes in the software. Configuration management practices include configuration identification, change control, ( ) and configuration audit.
A. milestones marking
B. status reporting
C. stakeholder management
D. quality audit
【答案】B
【解析】
软件配置管理用来跟踪并控制软件的变化。配置管理过程包括配置标识.变更控制.( )和配置审计。
A. 里程碑标记
B. 状态报告
C. 干系人管理
D. 质量监查